Project Tracker
Development of the flood drainage system in Kulhudhuffushi City

ބެންޒީ ޓްރޭޑިންގ ޕްރައިވެޓް ލިމިޓެޑް
Project Cover PhotoPhase 2 / 2 — Building a culvert.
100%
Overall Progress
1,198,672.43
Budget
Dec 03, 2025
Start Date
Mar 27, 2026
Estimated End
Phases2/2 Completed
Building a culvert.

Building a culvert.
Dec 25, 2025 — Mar 12, 2026
Progress100%
Milestones3/3
Digging work
Building work.
Concrete work.
Project Photos