Project Tracker

Work to improve the water drainage system in Kulhudhuffushi City.

Project cover
Benzi Trading Private Limited
Phase 2 / 2 — Building a culvert.

75%

Overall Progress

1,198,672.43

Budget

Dec 03, 2025

Start Date

Mar 12, 2026

Estimated End

Phases1/2 Completed
Digging canals, junctions, and burying pipes.
Building a culvert.
Phase photo

Building a culvert.

50%
Dec 25, 2025Mar 12, 2026
Progress50%
Milestones1/2
Digging work
Building work.

Project Photos

Photo 1
Photo 2
Photo 3
Photo 4